The Minister of State for Works, Mr Bello Goronyo, has warned the contractors handling 750 kilometers Sokoto-Gusau-Funtua-Zaria Road project against unnecessarily delaying the completion of the project.
Goronyo made the warning during an inspection tour of the ongoing road project along Dange to Shuni to Tureta in Sokoto State to Talata Mafara, Maru and Bungudu in Zamfara, on Sunday.
He reiterated the Federal Government’s commitment to the timely completion of the reconstruction of project in order to ease the sufferings of Nigerians plying the roads.
He said the inspection was part of President Bola Tinubu’s marching orders given to the ministry to ensure that the ongoing projects were executed as schedule to make them motorable for users.
“I am leading a team comprising the Directors and other ministry’s officials on the inspection tour to projects from Sokoto, Zamfara, Katsina and Kaduna States to ensure quality and seamless projects.
” I am representing the Minister of Works, Dave Umahi, to assess the level work and accomplishment of the specifications,” the minister said.
He reminded the contractors and officials handling the project of the need to comply with all the contractual agreements as well as to ensure the speedy and quality job.
The minister appreciated the contractors handling Sokoto-Tureta-Mafara section that achieved about 27 per cent coverage and urged them to sustain the tempo on speed and quality execution of the project.
He observed that contractors had faced a hitch for non payment of compensation to the owners of properties on the road, adding, “however, with the payment of compensation by Gov. Ahmad Aliyu, full work had resumed in all the places.”
Goronyo commended Aliyu for the payment of the compensation and security support to the workers, hence safeguarding their lives.
On the Mafara-Maru-Gusau project portion, the minister lamented that 16 per cent coverage was not encouraging, saying that the Federal Government was considering limiting the contractors to 37 kilometers and award the rest portion of 68 kilometers to another firm.